Projects
Construction Projects:

- Hanks Road Culvert Replacement
Monday, March 18th, the contractor moved their equipment in and began construction on March 19th. They are trenching across the roadway and installing a new culvert pipe among other items of work. Hanks road will be closed March 20th and March 21st to install the new culvertIt will again be closed the following March 25th to allow for paving. A minimum of lane of traffic will remain open at all other times.  Click here to see the vicinity map showing the project location as well as the proposed detour route.

 - Evans Road Culvert Replacement
Construction started March 2019

Maintenance Projects:

- Bituminous Surface Treatment (BST)
Also referred to as "chip seal" has an estimated start time for April 2019.

- Crushing and Stockpiling at Highland Quarry and C. Moore Quarry
Work started in 
March at the Highland Quarry and will continue through early April.  Once crushing has been completed at Highland Quarry, work will begin at the C Moore Quarry.  Work at C Moore Quarry will continue through the end of April.




















































       
       
       

       
      Benton County    620 Market Street    Prosser, Washington 99350
      Phone: (509) 786-5710 or (509) 783-1310
      Site Map   |   Employment   |   Powered by MunicipalCMS
      E-notify RSS Feeds Twitter Facebook 
       
      0