UPDATE: Phase 3 of Nine Canyon Road Project
 
Posted on Monday June 11, 2018
 
Nine Canyon Rd Phase III detour map and project photos.
 
UPDATE:
The roadway excavation and embankment were completed last week (June 4-8), and the contractor is now working on placing the base course rock. The project is anticipated to finish in early August 2018.

NineCanyon1NineCanyon2
NineCanyon3NineCanyon4

ORIGINAL ALERT:
The Benton County Road Department will be starting Phase 3 of the Nine Canyon Road project on Monday, February 26, 2018 with anticipated completion around June 29, 2018.

Premier Excavation will be realigning portions of Nine Canyon Road and will be paving a 2.65 mile section of the road, to continue the project from Phase 2.

Click the image below for printable, PDF version of the detour map.
022618_NineCanyonDetour
 

 